Login
Toggle navigation
Menu
Home
About PBA
Our Mission
History & Map
Board of Directors
Annual Meeting
For Members
Neighbor Directory
Member Newsletter
Blocks & Captains
PBA Sitters
Volunteer Opportunities
Security
PBA Security
Meet the Officers
Crime Trackers
Committees
Parks
Security
Social
Traffic
Zoning & Variance
Resources
PBA News
Filming in PBA
City Projects in PBA
City of Atlanta Information
E. Rivers Elementary School
Haynes Manor Garden Club
Contact Us
Return to List
COA Updates for PBA
Posted on Oct 28th, 2022
DWM provides communication updates to PBA leadership regarding projects and work schedules. Please visit the page for
City Projects in PBA
(found under the Resources tab) for additional information.
Week of 10/31/2022:
Woodward Way Pump Station #1 Improvements Project
2344 Havenridge Drive NW – Restoration
Week of 10/24/2022:
Woodward Way Pump Station #1 Improvements Project
2344 Havenridge Drive NW – Restoration
Week of 10/17/2022:
Woodward Way Pump Station #1 Improvements Project
2344 Havenridge Drive NW – Restoration
Week of 10/10/2022:
Woodward Way Pump Station #1 Improvements Project
2344 Havenridge Drive NW – Restoration
Week of 9/26/2022:
Woodward Way Pump Station #1 Improvements Project
2344 Havenridge Drive NW – Restoration
Week of 9/19/2022:
Woodward Way Pump Station #1 Improvements Project
2344 Havenridge Drive NW – Restoration
Week of 9/12/2022:
Woodward Way Pump Station #1 Improvements Project
2344 Havenridge Drive NW – Restoration
Week of 9/05/2022:
Woodward Way Pump Station #1 Improvements Project
2344 Havenridge Drive NW – Restoration
Week of 8/29/2022:
Woodward Way Pump Station #1 Improvements Project
2344 Havenridge Drive NW – Restoration
Week of 8/15/2022:
Woodward Way Pump Station #1 Improvements Project
2344 Havenridge Drive NW – Restoration
Week of 8/8/2022:
Woodward Way Pump Station #1 Improvements Project
2344 Havenridge Drive NW – Restoration
Week of 8/1/2022:
Woodward Way Pump Station #1 Improvements Project
2344 Havenridge Drive NW – Restoration
Week of 7/18/2022:
Woodward Way Pump Station #1 Improvements Project
2344 Havenridge Drive NW – Restoration
Week of 7/11/2022:
Woodward Way Pump Station #1 Improvements Project
2344 Havenridge Drive NW – Restoration
Week of 7/04/2022
Woodward Way Pump Station #1 Improvements Project
2344 Havenridge Drive NW – Restoration
Week of 6/20/2022
Woodward Way Pump Station #1 Improvements Project
2344 Havenridge Drive NW – Restoration